Coating Installation

Xypex coating is applied with a semi-stiff nylon bristle brush, push broom (for large horizontal surfaces), or specialized spray equipment.

coating install-01

General Information


Weather and Concrete Conditions  

  1. The Xypex treatment must not be applied under rainy conditions or when ambient temperature is below 40ºF (4ºC).
  2. Because Xypex requires moisture to initiate the crystalline waterproofing process, all concrete, whether fresh or old, must be saturated with water. (See Wetting Concrete below.) 
  3. The concrete surface must be a minimum of 20 hours old before application of the Xypex coating treatment.
  4. For fresh concrete, the period between 24 hours and 72 hours is the optimum time within which to apply Xypex, as the new concrete is still “green” and requires very little pre-watering. 

Coverage
For normal surface conditions, the coverage rate for each Xypex coat is 1.25 to 1.5 lb./sq. yd. (0.65 - 0.8 kg/m2).


Next section: Preparation

Scroll to top